From Wellington Bombers to Formula 1, Mather & Co and Cube Design create the Silverstone Experience
– Paul Lee
The Silverstone Experience, a journey through the home of British motor racing, is to open in a refurbished WW2 RAF hangar later this month.
The £20m (US$24.6m, €22.3m) development has taken seven years to bring to fruition and included the restoration of the 4,000sq m (13,100sq ft) hangar.
Led by architect Jane Lock-Smith of Cube Design, the project required more work than was initially expected, with the hangar having to be stripped right back to its steel frame.
Sally Reynolds, CEO of Silverstone Heritage, told CLAD: "The condition of the building was far worse than expected. We had to take the roof off, reinforce the frame and then repaint and reclad the whole building."
Elaborating further, Lock-Smith told us: "Careful restoration had to be undertaken, including the foundations around the base of the hangar, replacement of some steelwork sections that had corroded, and careful assessment for the re-cladding of the hangar. The hangar is so delicately designed that the cladding system could not be supported off the original frame."
A modern new entrance building was created in a similar style to the hangar and chameleon-like cladding was fitted that changes colour in the light and shade. Special lighting has been installed so visitors can see the internal structure of the hangar and a new extension, housing a shop, a café and archive, was also built.
Sports museum specialists Mather & Co were responsible for the design of the exhibition and interactive features, with 20 activities for visitors to try, including changing an F1 tyre, climbing into a replica 1940s grand prix car and piloting a Wellington bomber in a simulator.
Paul Lee, senior project designer at Mather & Co, said the intention had been to bring out Silverstone's rich heritage and social community in the designs and story-telling for all demographics, not just motorsport fans: "We've brought to life all elements of Silverstone's rich history, from its roots as a base for wartime Wellington bombers to the modern-day technology seen in the Formula 1 cars that race here today."
The hangar was one of six built during the construction of RAF Silverstone, which began in 1941. The site was subsequently taken over as a motor racing circuit after the war, with only one of the six hangars remaining.
Originally due to open in July 2019, delays became inevitable in June when construction firm Shaylor Group went into administration. The Silverstone Experience opens on October 25th.
Silverstone Experience National Lottery Heritage Fund British Racing Drivers' Club Silverstone Silverstone Heritage Mather & Co Cube DesignSilverstone Experience delayed after contractor enters administration
Silverstone Experience gearing up for June opening
Home of British motor racing to get permanent museum as Silverstone Heritage Experience gets green flag
Europe's premier Evian Spa unveiled at Hôtel Royal in France
Clinique La Prairie unveils health resort in China after two-year project
GoCo Health Innovation City in Sweden plans to lead the world in delivering wellness and new science
Four Seasons announces luxury wellness resort and residences at Amaala
Aman sister brand Janu debuts in Tokyo with four-floor urban wellness retreat
€38m geothermal spa and leisure centre to revitalise Croatian city of Bjelovar
Two Santani eco-friendly wellness resorts coming to Oman, partnered with Omran Group
Kerzner shows confidence in its Siro wellness hotel concept, revealing plans to open 100
Ritz-Carlton, Portland unveils skyline spa inspired by unfolding petals of a rose
Rogers Stirk Harbour & Partners are just one of the names behind The Emory hotel London and Surrenne private members club
Peninsula Hot Springs unveils AUS$11.7m sister site in Australian outback
IWBI creates WELL for residential programme to inspire healthy living environments
Conrad Orlando unveils water-inspired spa oasis amid billion-dollar Evermore Resort complex
Studio A+ realises striking urban hot springs retreat in China's Shanxi Province
Populous reveals plans for major e-sports arena in Saudi Arabia
Wake The Tiger launches new 1,000sq m expansion
Othership CEO envisions its urban bathhouses in every city in North America
Merlin teams up with Hasbro and Lego to create Peppa Pig experiences
SHA Wellness unveils highly-anticipated Mexico outpost
One&Only One Za’abeel opens in Dubai featuring striking design by Nikken Sekkei
Luxury spa hotel, Calcot Manor, creates new Grain Store health club
'World's largest' indoor ski centre by 10 Design slated to open in 2025
Murrayshall Country Estate awarded planning permission for multi-million-pound spa and leisure centre
Aman's Janu hotel by Pelli Clarke & Partners will have 4,000sq m of wellness space
Therme Group confirms Incheon Golden Harbor location for South Korean wellbeing resort
Universal Studios eyes the UK for first European resort
King of Bhutan unveils masterplan for Mindfulness City, designed by BIG, Arup and Cistri
Rural locations are the next frontier for expansion for the health club sector
Tonik Associates designs new suburban model for high-end Third Space health and wellness club
Aman sister brand Janu launching in Tokyo in 2024 with design by Denniston's Jean-Michel Gathy
Why shouldn’t sports facilities be beautiful? Across Asia, architects are creating landmark buildings for the public, discovers Christopher de Wolf